Project in Process:

Anticipated Start Date

Impact of Project

Cafeteria Noise Panels Fall 2023 Install Acoustic Panels to Improve Noise Levels in Cafeteria
Additional security cameras Spring 2024 Prioritizing the safety and well-being of our students, staff and facilities, four new security cameras (2 interior/2 exterior) are being added.
Replace chiller unit to gym* Summer 2024 Work is related to improved air quality and circulation (AC/Heat/Circulation system)
DHW Replacement   Summer 2024    Domestic Hot Water System Replacement
     

Completed Projects:

major summer cleaning Summer 2023 Over the summer all school buildings underwent their major summer cleaning (deep clean of all major educational spaces - furniture and fixtures are removed from all classrooms, the floors/walls are deep cleaned and then the roos are restaged).
Floor stripped and waxed Summer 2023 Stripping and refinishing is the process of removing old layers of wax and dirt, restoring the floors to a like-new appearance and protecting it from future damage.
Exterior facade repair Summer 2023 Work related to ongoing maintenance and prevention of water intrusion.
Masonry Repairs Summer 2023 Repair Waterproofing and Masonry to Mitigate window Leaks. Repair Damaged Drywall at Interior Windows
     

Grounds Related Projects:

 

*Denotes a Capital Project managed by the City