Hart Elementary School Facilities Projects(Updated February 2024) |
||
Project in Process: |
Anticipated Start Date |
Impact of Project |
Mechanical repairs | Summer 2023 | Work is related to improved air quality and circulation (AC/Heat/Circulation system) |
Exterior facade repair | Summer 2023 | Work related to ongoing maintenance and prevention of water intrusion. |
Additional security cameras | Spring 2024 | Prioritizing the safety and well-being of our students, staff and facilities, four new security cameras (2 interior/2 exterior) are being added. |
Front security vestibule* | Spring 2024 | Piroritizing the safety and well-being of our students, staff and facilities, a secure entrance area is beign created. This project is a capital project which is eligible for state funding. The state reimbursement request is being submitted in August 2023. |
Boiler Replacement | Fall 2023 | Replacing Unrepairable Sectional Boiler with Two High Efficiency Boilers |
Electronic door control for exterior doors* | Summer 2024 | Prioritizing the safety and well-being of our students, staff and facilities, keyless entry solutions are being added to all school facilities as part of our district-wide adoption of integrated security systems. |
Heat Exchanger replacement | Spring 2024 | This project will replace an existing heat exchanger which is at the end of its useful life. |
Domestic Hot Water Tank Replacement | Spring 2024 | The DHW system at the school is at the end of it's usefull life and will be replaced as part of this project. |
Completed Projects: |
||
major summer cleaning | Summer 2023 | Over the summer all school buildings underwent their major summer cleaning (deep clean of all major educational spaces - furniture and fixtures are removed from all classrooms, the floors/walls are deep cleaned and then the roos are restaged). |
Floor stripped and waxed | Summer 2023 | Stripping and refinishing is the process of removing old layers of wax and dirt, restoring the floors to a like-new appearance and protecting it from future damage. |
Front entrance | Summer 2023 | Repaved front walkway and ADA ramp |
Floor repair | Summer 2023 | From time to time, restorative floor care is needed to help restore the floors and prevent any permanent damage. |
Converted two underutilized offices into a new classroom. | Summer 2023 | |
Replaced main office paging system | Summer 2023 | |
Grounds Related Projects: |
||
Walking path | Summer 2023 | The City of Stamford has established a walking path that creates a natural greenway from the West Side to Downtown. The path is accessible from Hart grounds. |
Containers | Summer 2023/Fall 2023 | Containers are being removed or replaced with newer equipment owned by SPS. Containers are used for on-site storage of furniture and equipment. |
*Denotes a Capital Project managed by the City |